RO YOUTH 089 444 1394
JYSK Tullamore — Tullamore, Co. Offaly
Register

P-05 Tullamore, Co. Offaly · Retail fit-out

JYSK Tullamore

Large-format retail drylining package delivered ahead of store opening, including ceiling areas and beam boxing.

Location
Tullamore, Co. Offaly, Ireland
Role
Drylining subcontractor - walls, ceilings, beams
Scope
Partitions, ceiling boarding, beam encasement, tape & joint
Status
Completed

01 The record

Retail Fit-Out Works

Everything below is taken from the job itself — who it was for, what the package covered, and photographs from site.

Project
JYSK Tullamore
Location
Tullamore, Co. Offaly, Ireland
Type
Commercial Retail Fit-Out
Client / Brand
JYSK (Scandinavian home furnishing retailer)
Our Role
Drylining subcontractor - walls, ceilings, beams
Main Subcontractor
DJ Interiors
Scope of Works
Partitions, ceiling boarding, beam encasement, tape & joint
Status
Completed

02 The job

01

About the Project

JYSK is an international Scandinavian retail brand specialising in home furnishings, bedding, and garden products, operating thousands of stores across Europe. The Tullamore store represents one of JYSK's Irish openings, delivering a large-format retail unit to the Tullamore market in Co.

Offaly. The fit-out of a large retail unit of this nature requires precise, high-output drylining works - including extensive ceiling areas, beam encasements to exposed structural steel, and partition walls - all delivered to a tight commercial programme ahead of the store's Grand Opening.

02

Our Contribution

RO Youth Construction was engaged by DJ Interiors as the specialist drylining subcontractor for the JYSK Tullamore fit-out. Our team carried out the full internal drylining package - installing all partition walls, large-area ceiling boarding, and beam encasement boxes to the structural steel throughout the unit.

All plasterboard joints were taped and jointed to a smooth commercial finish, ready for decoration and shop-fitting. The beam encasement works were a key feature of the ceiling scope, requiring accurate boxing and boarding around the steel frame to achieve the clean, finished retail look seen at Grand Opening.

Our team maintained high daily output throughout, supporting the store's delivery on time.

03 Scope delivered

  • Installation of all internal partition walls throughout the retail floor space
  • Full ceiling plasterboard installation - large-area commercial ceiling boarding
  • Beam encasement works - all structural steel beams boxed and boarded in plasterboard
  • Tape and joint finishing to all plasterboard surfaces (walls, ceilings, and beams)
  • Works coordinated with mechanical, electrical and shop-fitting trades on site
  • Commercial retail fit-out standard maintained throughout - high-quality finish
  • Works carried out for DJ Interiors as specialist drylining subcontractor

04 Site photography

From first fix to finished areas.

5 photographs from this job. Site records, not renders.

Ceiling plasterboard with beam encasement - corridor view
Ceiling plasterboard with beam encasement - corridor view
Gyproc wall boarding and taped joints
Gyproc wall boarding and taped joints
Large retail ceiling - beam encasement in progress
Large retail ceiling - beam encasement in progress
Full ceiling and beam encasement - wide span retail area
Full ceiling and beam encasement - wide span retail area
Beam boxing detail - tape & joint applied
Beam boxing detail - tape & joint applied

Contact

Send the drawings.

Mark the areas, tell us the dates. We come back with crew availability — and we say straight out if we cannot hold them.